Home NewsEngineering Technology & Innovation Europe Halfway mark passed in €2bn project to lay the world’s longest subsea cable between Norway and UK

Halfway mark passed in €2bn project to lay the world’s longest subsea cable between Norway and UK

Construction of the longest subsea power cable in the world has now passed the halfway point and achieved a major engineering feat to enable Norway’s zero carbon hydro energy to be shared with the UK.

North Sea Link, a joint venture project between National Grid in the UK and Norwegian system operator Statnett, is a subsea electricity cable that will connect the UK and Norwegian electricity grids.

Before being able to lay the cable in Norway, the team first had to tackle manoeuvring the cable through a lake, which cannot be accessed by the size of the vessel usually required for cable laying.

Instead, the team have transported materials piece by piece to build their own custom-made floating platform. The operation is the first of its kind in this scale in Norway, and the construction of the platform had an average of 25 people working on it daily over the course of 11 days. This unique operation in Suldalsvatnet, marks the start of the cable laying on the Norwegian side.

Working at depths of up to 210 metres, the laying of the 2.8km parallel subsea cables was executed from a 43 x 15 metre platform – equivalent to the size of two tennis courts.

The equipment required to lay the cable was then installed on the platform, and within 12 hours, 150 tonnes of cable were loaded on board. The platform held all the necessary equipment that is usually found on offshore cable laying vessels.

Nigel Williams, Construction Director for National Grid North Sea link said:

“The engineering that has taken place to lay high-voltage cables below the seabed is remarkable. The difficult terrain, the depth of the waters, and all in amidst of operating during a pandemic has made it extremely challenging. Nevertheless, we have powered through and remained on track with our project timelines.”

The next milestone is to lay the cable out from the fjords in Suldal, to the North Sea this summer.

This work will be carried out throughout the remainder of the year, and by 2021 the two parallel 720km cables between Cambois, Northumberland in the UK and Kvilldal, in Norway will have been completed to make North Sea Link the longest subsea power cable interconnector in the world.

By 2021, North Sea Link will be operational and the 1.4-gigawatt electricity interconnector will allow the UK to import enough clean energy to power up to 1.4 million homes.

The 2 billion Euro project is National Grid’s fifth under water electricity cable, connecting  British homes into Norway’s biggest hydro-dam – known as Europe’s green battery – and one hundred per cent of the electricity travelling through it will be from zero carbon sources.

North Sea Link will provide additional transmission capacity for electricity to be traded more efficiently, and will contribute to downward pressure on electricity prices when demand is high on one side of the cable.

North Sea Link will enable both countries to maximise the use of these natural resources for the benefit of consumers in Norway and the UK.

When wind generation is high and electricity demand is low in the UK, North Sea Link will allow up to 1,400MW of power to flow from the UK, conserving water in Norway’s reservoirs.

When demand is high in the UK and there is low wind generation, up to 1,400MW can flow from Norway, helping to ensure secure electricity supplies.

Construction of the longest subsea power cable in the world has now passed the halfway point and achieved a major engineering feat to enable Norway’s zero carbon hydro energy to be shared with the UK.

North Sea Link, a joint venture project between National Grid in the UK and Norwegian system operator Statnett, is a subsea electricity cable that will connect the UK and Norwegian electricity grids.

Before being able to lay the cable in Norway, the team first had to tackle manoeuvring the cable through a beautiful lake, which cannot be accessed by the size of the vessel, usually required for cable laying.

Instead, the team have transported materials piece by piece to build their own custom-made floating platform. The operation is the first of its kind in this scale in Norway, and the construction of the platform had an average of 25 people working on it daily over the course of 11 days. This unique operation in Suldalsvatnet, marks the start of the cable laying on the Norwegian side.

Working at depths of up to 210 metres, the laying of the 2.8km parallel subsea cables was executed from a 43 x 15 metre platform – equivalent to the size of two tennis courts.

The equipment required to lay the cable was then installed on the platform, and within 12 hours, 150 tonnes of cable were loaded on board. The platform held all the necessary equipment that is usually found on offshore cable laying vessels.

Nigel Williams, Construction Director for National Grid North Sea link said:

“The engineering that has taken place to lay high-voltage cables below the seabed is remarkable. The difficult terrain, the depth of the waters, and all in amidst of operating during a pandemic has made it extremely challenging. Nevertheless, we have powered through and remained on track with our project timelines.”

The next milestone is to lay the cable out from the fjords in Suldal, to the North Sea this summer.

This work will be carried out throughout the remainder of the year, and by 2021 the two parallel 720km cables between Cambois, Northumberland in the UK and Kvilldal, in Norway will have been completed to make North Sea Link the longest subsea power cable interconnector in the world.

By 2021, North Sea Link will be operational and the 1.4-gigawatt electricity interconnector will allow the UK to import enough clean energy to power up to 1.4 million homes.

The €2 billion Euro project is National Grid’s fifth under water electricity cable, connecting  British homes into Norway’s biggest hydro-dam – known as Europe’s green battery – and one hundred per cent of the electricity travelling through it will be from zero carbon sources.

North Sea Link will provide additional transmission capacity for electricity to be traded more efficiently, and will contribute to downward pressure on electricity prices when demand is high on one side of the cable.

North Sea Link will enable both countries to maximise the use of these natural resources for the benefit of consumers in Norway and the UK.

When wind generation is high and electricity demand is low in the UK, North Sea Link will allow up to 1,400MW of power to flow from the UK, conserving water in Norway’s reservoirs.

When demand is high in the UK and there is low wind generation, up to 1,400MW can flow from Norway, helping to ensure secure electricity supplies.

Share this




Subscribe now and stay up to date for our forthcoming reports and current news

This website uses cookies to ensure you get the best experience on our website. Cookies Policy

Cookies Policy | Preferences
Welcome to Waterbriefing Global

We care about your privacy. In order to run a successful website, we and certain third parties use cookies to personalize content and ads, to provide social media features, and to analyze our traffic. You consent to our cookies if you continue to use our website.